BMS & EMS have been growing since 6 years when the first phase start; due to the good results that have been achieved since the implementation the facilities manager has been continue using the system to analyze all the consumption and process environmental operation related to the HVAC
This project includes
The BMS design and construction included more than 15,000 feet of communication line over on a daisy-chain topology with different protocols including BacNet and Modbus, created below of 8 Ethernet Segments over IP, Those challenges were ultimately overcome, and the systems installed were tied-into all building.
The Data Base programs were develop under the maximize efficiency standard including sequence of operation with economizer, setpoints resets and occupancy, taking care on the environmental conditions required for the validated quality process.
One of the success strategies on this project was the management and team communication, with the facilities staff to accommodate all the Sequence of Operation listen the field experience from the plant engineers under the equipment operation. Validation and Commissioning were successful because the design was detailed before to start the project execution.
Overall, the initial project was around of 70% of the full BMS project.
The project had been develop with process running and plugin and play each area limited by time to avoid affect the process quality, the initial project finished under budget within the schedule that was dynamically updated over the course of the project. later of that the database has been growing integrating in phases new construction areas and new process equipment as per customer needed.