OUR WORK WITH
Develop: 2020 - 2021
Type: BMS / EMS / Biosafety Level 3
Process: Biosafety Microbiology Laboratory
Sizes: 20,000 SqFt
Location: 9566 Railroad Dr. El Paso, TX 79924
Contractor: The Garick Group, Inc.
(915) 779-5727 PM – Paul Porras
Commissioning By: CARDINA Engineering Commissioning -
Carlos E. Arguijo, P.E., LEED AP BD+C (915)-373-6030
CASE STUDY
The City Of El Paso and the Alegro Engineering, L.P. engaged BUILDTECH AUTOMATION INC. to provide a BUILDING AUTOMATION SYSTEM
solution for the new project named “EXPANSION OF PUBLIC HEALTH LABORATORY COVID-19 TESTING AND COVID-19 RESPONSE STORAGE AND LOGISTICS FACILITY”
.
BUILDTECH AUTOMATION INC. as a Professional Engineering Group collaborate on the design review and controls sequence of operations adequations for these Laboratories category Biosafety Level 3 (BSL3).
Not only did this project present technical challenges based on complexity of the systems and controls being implemented, but the COVID-19 pandemic created manpower, shipping, and fabrication issues that contributed to difficulties faced in completing this project. Those challenges were ultimately overcome, and the systems installed were tied-into Covid19 studies and analysis.
The new building and HAVC Installation consist mainly of:
Due to an increase in the pandemic the project was developed as a fast-track project.
Overall, this project had several design, logistical, and pandemic-related obstacles that were overcome through the input and persistence of the BUILDTECH team.
Despite these challenges, after hundred of commissioning together with the engineers the project was finished under budget within the schedule that was dynamically updated over the course of the project.